Datacenter migration
Due to rapid growth this organization had less than one year to complete four distinct phases:
- Build new Infrastructure and a new up-scaled DataCenter
- Migrate the virtual servers in current DC to the new location
- Recommission up-to-par rack devices from old to new
- Decommission old Infrastructure and DC
The Project scope covered the technical server migration and system implementation in the upgraded hyper-V cluster (2008-2012).
Hardware partner: Dell
Hardware and fabric setup: SLTN
Network: Cisco, Neon-networking